In order to supply water to the Kish south Kaveh steel company were estimated that 150,000 cubic meters is daily needed. Therefore, on its southern part of the company located in Bandar Abbas Persian Gulf Mining and Metal Industries Special Economic Zone the construction of desalination plants had been added to agenda. In order to supply this complex water, a pipeline project to transfer water from the sea to the beach was defined. Our company started its activity in project operations from March 2013 which included the implementation of two parallel pipelines size of 1000 mm length of approximately 1900 m in BOX CULVERT (total length of about 4 km) from the water harvesting industry on the waterfront of Persian Gulf Mining and Metal Industries Special Economic Zone to the location of construction of desalinations facilities of Kish south Kaveh steel company, Including the construction and installation of pipe racks steel structures and metal platform.